Release Schedule
Tagging Deadline:
Public Release:
Release Checklist
2 Working Days Before the Tagging Deadline
- (QA) Check whether all issues assigned to the release milestone are resolved1 .
- (QA) Ensure that there are no outstanding merge requests in the private repository1 (Subscription Edition only).
- (QA) Ensure all merge requests marked for backporting have been indeed backported.
Before the Tagging Deadline
- (QA) Inform Support/Marketing of impending release (and give estimated release dates).
- (QA) Check Perflab to ensure there has been no unexplained drop in performance for the versions being released.
- (SwEng) Update API files for libraries with new version information.
- (SwEng) Change software version and library versions in
configure.ac(new major release only). - (SwEng) Rebuild
configureusing Autoconf ondocs.isc.org. - (SwEng) Update
CHANGES. - (SwEng) Update
CHANGES.SE(Subscription Edition only). - (SwEng) Update
README.md. - (SwEng) Update
version. - (SwEng) Build documentation on
docs.isc.org. - (QA) Check that all the above steps were performed correctly.
- (QA) Check that the contents of release notes match the merge requests comprising the releases.
- (QA) Check that the formatting is correct for text, PDF, and HTML versions of release notes.
- (SwEng) Tag the releases2 . (Tags may only be pushed to the public repository for releases which are not security releases.)
- (SwEng) If this is the first tag for a release (e.g. beta), create a release branch named
release_v9_X_Yto allow development to continue on the maintenance branch whilst release engineering continues.
Before the ASN Deadline (for ASN Releases) or the Public Release Date (for Regular Releases)
- (QA) Verify GitLab CI results for the tags created and prepare a QA report for the releases to be published.
- (QA) Request signatures for the tarballs, providing their location and checksums.
- (Signers) Validate tarball checksums, sign tarballs, and upload signatures.
- (QA) Verify tarball signatures and check tarball checksums again.
- (Support) Pre-publish ASN and/or Subscription Edition tarballs so that packages can be built.
- (QA) Build and test ASN and/or Subscription Edition packages.
- (QA) Notify Support that the releases have been prepared.
- (Support) Send out ASNs (if applicable).
On the Day of Public Release
- (Support) Wait for clearance from Security Officer to proceed with the public release (if applicable).
- (Support) Place tarballs in public location on FTP site.
- (Support) Publish links to downloads on ISC website.
- (Support) Write release email to bind-announce.
- (Support) Write email to bind-users (if a major release).
- (Support) Update tickets in case of waiting support customers.
- (QA) Build and test any outstanding private packages.
- (QA) Build public packages (
*.deb, RPMs). - (QA) Inform Marketing of the release.
- (QA) Update the internal BIND release dates wiki page when public announcement has been made.
- (Marketing) Post short note to Twitter.
- (Marketing) Update Wikipedia entry for BIND.
- (Marketing) Write blog article (if a major release).
- (QA) Ensure all new tags are annotated and signed.
- (SwEng) Push tags for the published releases to the public repository.
- (SwEng) Merge the automatically prepared
prep 9.X.Ycommit which updatesversionand documentation on the release branch into the relevant maintenance branch (v9_X).
-
If not, use the time remaining until the tagging deadline to ensure all outstanding issues are either resolved or moved to a different milestone. ↩︎
-
Preferred command line:
git tag -u <DEVELOPER_KEYID> -a -s -m "BIND 9.X.Y[alphatag]" v9_X_Y[alphatag], where[alphatag]is an optional string such asb1,rc1, etc. ↩︎